How long does the assembly take? In this test, we already have the carbor support plate with all holes drilled, and trays mounted, as well as the threaded rods.

13:25 - Start with the detector as show, with ribbons attached.

14:07 - Cables removed. There were 3 M2 philipshead screws where the head was almost stripped, took extra time to get them out
14:15 - top removed and cable top brackets off
14:23 - blocks 2, 4, 6 (connectors D,E,F) removed
14:34 - blocks 1, 3, 5 (connectors A,B,C) removed
Components laid out, ready for re-assembly
14:32: start reassembly, block 1 (connector A) threaded and inserted
15:00 - first block 1 finished
15:18 - third block 1 finished
15:23 - start threading blocks 3 (connectors B)
15:56 - 3rd block 3 finished
15:56 - start placing blocks 5
16:07 - blocks 5 (connectors C) finished
16:32 - start blocks 6 (connectors D) finishedcks 2
16:49 - blocks 4
17:03 - blocks 2
17:17 - finished blocks 2
17:21 - cover back on

Total re-assembly time: 2h 50m