Mock data challenge deadlines

I took this list of dates from an email message sent by Bill Zajc to the phenix-comp-l mailing list on 25-Sept 1997.

data task
15-Oct-1997 PHASE 0 Completion of STAF Transition
(all systems in STAF, all "raw" tables spec-ed)
15-Dec-1997 Preliminary response packages for all sub-systems
written (i.e., simulates ADC's, leading/trailing
edges, etc. starting from PISA results read into STAF).
15-Feb-1998 Raw tape simulators in production mode (PISA output
in, fake data tape out, with simulation of noise,
cross-talk, slewing, dead-channels driven by STAF
tables/controls.)
15-Mar-1998 PASS 0 (calibration pass) in production mode
15-Apr-1998 PASS 1 (reconstruction pass) in production mode
(should also include preliminary PID code)
15-May-1998 "Physics analyses in production"
22-June-1998 Present results at Ames

Here is a proof that milestones are not worth the paper they are written on.


updated April 27, 1998
John Sullivan (sullivan@lanl.gov)