EDM CD-1 Review

 

General Information

Agenda for August 7-9, 2006 Review at LANL 2-Aug-06

Hotel and Travel Information for Los Alamos 1-May-06

Detailed Directions 2-Aug-06

Social Schedule 3-Aug-06

 

CD-1 Documents

Conceptual Design Report (CDR) 24-Jul-06

The scientific description of the neutron EDM experiment.

Preliminary Acquisition Strategy XX-Jul-06

DOE only management document.

Preliminary Project Execution Plan (PPEP) XX-Jul-06

The principal management document.

Preliminary Risk Management Plan 2-Aug-06

The approach to risk in the EDM project.

Preliminary Hazard Analysis 2-Aug-06

A safety analysis and the hazard mitigations for the project during construction

and the ensuing operation of the EDM experiment.

 

Support Documents

Summary Cost Estimate 2-Aug-06

Project Schedule 2-Aug-06

The PDF version of the EDM project schedule.

This schedule is constrained by budget authority and not by the technical challenges.

MS Project Schedule 2-Aug-06

The full EDM project schedule from Microsoft (MS) Project.

Version 2000 or newer of MS Project is required to make use of this file.

Project Controls Manual 3-Aug-06

Supporting management documentation for the PPEP.

 

DOE Committee Documents

Review Committee Contact Information XX-Jul-06

Breakout Reviewer Assignments XX-Jul-06

 

Reference Documents

Full Pre-proposal 24-Apr-02

Update of Pre-proposal 1-Feb-05

Fits and Uncertainty Principle 10-Nov-02